Highway 50 Bus/Carpool Lanes & Community enhancements

Description: County and City of Sacramento - on US-50 from the Watt Ave to Sunrise Boulevard - HOV lanes and community enhancements

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City La Riviera, Rancho Cordova, Rosemont, Sacramento
Zip Code 95670, 95742, 95826, 95827
 
Senate District
01, 06
Assembly District 10
Congressional District 03, 05
 
Caltrans District
03
 
 
County/State Route Sacramento 50
Postmile Begin/End R  5.3 12.8
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  10888    1,953  
Lane Miles Added (HOV)  13.6    15  
Peak Period Time Savings (minutes)  794860    105,467  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Winder Bajwa (530) 741-4432   Winder_Bajwa@dot.ca.gov
Design (PS&E) Phase
Caltrans Winder Bajwa (530) 741-4432   Winder_Bajwa@dot.ca.gov
Right of Way Phase
Caltrans Winder Bajwa (530) 741-4432   Winder_Bajwa@dot.ca.gov
Construction Phase
Caltrans Jess Avila (530) 741-4533   jess.avila@dot.ca.gov
 
Corridor System Management Plan
Caltrans Jeff Pulverman (530) 741-4337   jeff.pulverman@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$80,000 $-32,389 $47,611
SLPP
$0 $7,214 $7,214
Non-bond Funding
State/Federal*
$5,000 $0 $5,000
Local**
$80,000 $-43,244 $36,756
Non Budgeted ETC
$0 $0 $0
 
Total**** $165,000 $-68,419 $96,581

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$5,000 $0 $5,000 $4,651
Design(PS&E)
$10,000 $-2,492 $7,508 $8,001
Right of Way
$2,875 $-1,000 $1,875 $2,114
Construction
$147,125 $-64,927 $82,198 $84,113
 
Total* $165,000 $-68,419 $96,581 $98,878

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2003 

09/01/2007 
 

 
07/01/2003 

09/01/2007 
100  07/08/2003 

06/25/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/01/2002 

04/01/2009 
 

 
02/01/2002 

04/01/2009 
100  02/01/2002 

04/10/2009 


Begin Right of Way Phase

End Right of Way Phase
10/01/2007 

01/01/2010 
 

 
10/01/2007 

01/01/2010 
100  02/23/2007 

04/10/2009 


Begin Construction Phase

End Construction Phase
01/01/2010 

01/01/2013 
 

 
01/01/2010 

01/01/2013 
100  10/26/2009 

05/10/2013 


-4 
Begin Closeout Phase

End Closeout Phase
01/01/2014 

01/01/2015 
 

 
01/01/2014 

01/01/2015 
75  05/10/2013 

08/15/2016 


-20 
Corridor System Management Plan
Adoption Date 03/01/2009    03/01/2009   
Implementation Date 07/01/2010    07/01/2010   
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 10888 1,953
Lane Miles Added (HOV) 13.6 15
Peak Period Time Savings (minutes) 794860 105,467

Bond Funding Cost
Adopted:
$80,000,000
Current Approved:
$47,611,000
Actual Expenditures:
$47,611,000

 

Status as of December 31, 2023.